Supervision Unit & Party A,
The project started on Sept 30, 2009 and completed on Oct 19, 2009 15 test piles have been finished, including 6 SZ1 test piles, 2 SZ2 test piles, 4 MZ2 test piles, 1 SZ3 test piles and 2 MZ3 test piles Pile caps, mudjack and ground levelling were completed before Oct 23, 2009 All the construction machinery has been removed Iin-Situ data has been handed over to the supervision unit The project will be tested after the curing period Please /confirm/i